Click Here to visit the ITRC Homepage
Click Here to visit the Mining Waste Home Page
Click Here for Tech-Reg Guidance Page
Click Here for Decision Tree
Click Here for Technology Overviews
Click Here for Case Studies
Click Here for Regulatory Issues
Click Here for Other Resources
Click Here for Additional Resources
Click Here for Appendices
Click Here to Contact UsClick Here to Contact Us
Click Here for Site Map


Case Study as part of a Web-based Technical and Regulatory Guidance

Fort Hood Site
Killeen, Texas

1. Site Information
1.1 Contacts
Valentine Nzengung
PLANTECO Environmental Consultants, LLC
337 South Milledge Avenue, Suite 202
Athens, GA 30605
Telephone: 706-316-3525
http://www.planteco.com

1.2 Name, Location, and Description
New landfill located at Fort Hood, Texas.

2. Remedial Action and Technologies
To ensure the sustainable operation of a newly constructed landfill at Fort Hood during its 30‑year projected operational life, the Department of the Army needed sustainable technologies to treat metals that were the contaminants of concern in the landfill leachate. A two-phase, engineered, green-treatment approach consisting of a microbial mat bioreactor (MMB) and multiple, small, containerized constructed treatment wetlands (CTWs) connected in series was evaluated at the field pilot scale. The basic conceptual design relied on the MMB to remove the bulk of the iron, manganese, and lead. The effluent from the MMB then flowed into the CTWs to remove the boron as well as additional iron, manganese, and lead. An oxidation/settling “pond” was included as the final stage of the CTWs to “polish” the treated effluent before disposal into the privately owned treatment works.

The final design used six CTW cells. Two large cells were 85" L × 56" W × 21" H, and four small cells were 48" L × 45" W × 22" H, for a total capacity of 535 gal:

Cell 1 (120 gal)—Duckweed (Lemnaceae)
Cell 2 (75 gal)—Cattails (Typha latifolia)
Cell 3 (120 gal)—Parrot feather (Myriophyllum aquaticum)
Cell 4 (35 gal)—Smartweed (Polygonum hydropiperoides)
Cell 5 (120 gal)—Bulrush (Scripus sp.)
Cell 6 (120 gal)—Aeration/settling

The smaller cells were enclosed in metal frames for support, and the larger did not have an external support frame. The CTW treatment train was set up as shown in Figures 2-1 and 2-2. Flow rates and residence times are shown in Table 2-1.

Image-Fort Hood Site Figure 2-1
Figure 2-1. Technology design.
Image-spacer
Image-Fort Hood Site Figure 2-2
Figure 2-2. Technology overview.

Table 2-1. Flow data for pilot test

Parameter
Microbial mat
bioreactor
Containerized constructed treatment wetlands
Flow rate in, gpm
                    2
                          1 gpm
Total volume treated, gal
                    11,520
                          5,760
Residence time, minutes
                    N/A
                          535
Residence time, hours
                    N/A
                          8.9


The treatment goals for the project were set as follows:

3. Performance
The MMB/CTW pilot test proved the viability of a modular MMB and CTW treatment system for metals removal from water. The MMB performed quite well prior to coating of the mat surface by undissolved iron precipitates. Even after the mats were coated with the precipitates, the system was still able to achieve some of the remediation goals.

The influent iron concentrations in Fort Hood landfill leachate used in this pilot test varied widely 6,980–15,700 µg/L. Interpretation of the results of this pilot test was complicated by the fact that the influent concentration of the different metals in the untreated leachate was not consistent throughout the duration of the test. Specifically, the initial metal concentration varied with each batch of leachate supplied for treatment. Additionally, the concentration of some metals in some batches of the supplied leachate was low and below the treatment goal. Although the microbial mats were initially effective in removing >80% of the influent iron at a flow rate of 2 gpm, the bioactive mat surface was quickly overwhelmed by the deposit of precipitated iron in the influent leachate, which reduced the removal efficiency to <60% of the influent iron concentrations (Figures 3-1 and 3-2). Because the bioreactor was overwhelmed by the suspended iron, there were few microbial mat bioactive sites available for adsorption or precipitation of manganese, lead, or boron.

Image-Fort Hood Site Figure 3-1
Figure 3-1. Loss of selected metals when comparing system influent and system effluent of the constructed treatment wetland.
(Negative values omitted for clarity.)
Image-spacer
Image-Fort Hood Site Figure 3-2
Figure 3-2. Percent loss of selected metals when comparing system influent and effluent of the microbial mat bioreactor.
(Negative values omitted for clarity.)

Overall the microbial mat bioreactor connected in series with the containerized treatment wetlands achieved the treatment goals (1,000 ppb) for iron. The boron levels in the landfill leachate were below the treatment goal, and so it is not possible to determine whether the MMB/CTW system can consistently remove boron to levels below the 5,000 µg/L treatment goal. The results of this pilot test highlight the need to install an iron precipitation and filtration step ahead of the modular microbial mat bioreactor. This goal can be easily accomplished by adding lime and sulfide to the influent landfill leachate and precipitating out the bulk of the iron. Pretreated landfill leachate, which contains little or no iron in suspension, should allow for optimum performance of the microbial mat bioactive surface.

A comparison of the treated effluent from the MMB and the CTW (Figures 3-1 and 3-2) indicates that the constructed treatment wetland was necessary to further remove some of the metals to the stringent compliance level. The treatment goals for iron (Table 3-1) were attainable by using the MMB alone.

Table 3-1. Treatment goals for pilot phase

Contaminant
Cleanup
concentration
Iron
0.1 ppm
Boron
0.5 ppm
All other metals
80% removal


4. Costs

5. Regulatory Challenges
None encountered

6. Stakeholder Challenges
Use of treated water for irrigation water on training ranges needed regulatory approval, which could be a lengthy process.

7. Other Challenges and Lessons Learned
The field application of a technology developed at the bench scale encounters a number of challenges when subjected to real-world conditions. The field-scale demonstration of the passive treatment of landfill leachate using microbial mats in series with multiple, containerized CTWs experienced a number of challenges, including the following:

8. References
Bender, J., M. C. Duff, P. Phillips, and M. Hill. 2000. “Bioremediation and Bioreduction of Dissolved U(VI) by Microbial Mat Consortium Supported on Silica Gel Particles,” Environmental Science and Technology 34(15): 3235–41.

Bender, J., J. P. Gould, Y. Vatcharapijarn, and G. Saha. 1991. “Uptake, Transformation and Fixation of Se(VI) by a Mixed Selenium Tolerant Ecosystem,” Water, Air, and Soil Pollution 59(3–4): 359–67.

Bender, J., J. P. Gould, Y. Vatcharapijarn, S. Young, and P. Phillips. 1994a. “Removal of Zinc and Manganese from Contaminated Water with Cyanobacterial Mats,” Water Environmental Research 66(5): 679–83.

Bender, J., R. F. Lee, and P. Phillips. 1995. “A Review of the Uptake and Transformation of Metals and Metalloids by Microbial Mats and Their Use in Bioremediation,” Journal of Industrial Microbiology and Biotechnology 14(2): 113–18.

Bender, J., and P. Phillips. 1995. “Biological Remediation of Mixed Waste by Microbial Mats,” Federal Facilities Environmental Journal 6(3): 77–85.

Bender, J., J. R. Washington, B. Graves, P. Phillips, and G. Abotsi. 1994b. “Deposit of Zinc and Manganese in an Aqueous Environment Mediated by Microbial Mats,” Water, Air, and Soil Pollution 75(3-4): 195–204.

Hedin, R. S., R. W. Nairn, and R. L. P. Kleinmann. 1994. The Passive Treatment of Coal Mine Drainage. U.S. Bureau of Mines Information Circular 9389.

ITRC (Interstate Technology & Regulatory Council). 2003. Technical and Regulatory Guidance for Constructed Treatment Wetlands. Washington, D.C.: Interstate Technology & Regulatory Council, Wetlands Team. www.itrcweb.org.

O’Niell, W. L., and V.A. Nzengung. 2000. “Treatment of Organic-Contaminated Water in Microbial Mat Bioreactors,” Symposium Series: Case Studies in the Remediation of Chlorinated and Recalcitrant Compounds, G. B. Wickramanayake, A. R. Gavaskar, J. T. Gibbs, and J. L. Means, eds. Columbus, Oh.: Battelle Press, 2(4): 347–52.

O’Niell, W. L., V. A Nzengung, and A. Adesida. 2000. “Treatment of Perchlorate-Contaminated Water in Microbial Mat, Algae, and Ebb-and-Flow Hydroponics Bioreactors,” Symposium Series: Case Studies in the Remediation of Chlorinated and Recalcitrant Compounds, G. B. Wickramanayake, A. R. Gavaskar, J. T. Gibbs, and J. L. Means, eds. Columbus, Oh.: Battelle Press 2(7): 101–06.

Image-spacer
This Web site is owned by ITRC • www.itrcweb.org
1250 H Street, NW • Suite 850 • Washington, DC 20005 • P: 202-266-4920 • F: 202-266-4937 • Sponsored by Environmental Council of the States

Disclaimer, Privacy, and Usage Policies

Click Here to Register for Free IBT Training on Document Click Here to visit the ITRC website Click Here to Go Back to the Previous Page Click Here to Visit Contaminated Dediments Team Public Page Click Here to Return to Title Page Click Here for a Printer Friendly Version of This Page