Case Study as part of a Web-based
Technical and Regulatory Guidance
Commerce/Mayer Ranch
Ottawa County, Oklahoma
1. Site Information
1.1 Contacts
Dr. Robert W. Nairn
The University of Oklahoma
School of Civil Engineering and Environmental Science
202 West Boyd Street, Room 334
Norman, OK 73019
Telephone: 405-325-3354
E-mail: [email protected]
1.2 Name, Location, and Description
The study site is located in the Tar Creek Superfund Site, part of the Picher
Mining Field, and the northeastern Oklahoma portion of the former Lead (Pb)
and Zinc (Zn) mining area known as the Tri-State Mining District (Figure
1-1). In this area, the ore deposit consists of Pb and Zn sulfides associated
with cherty carbonate host rock. The principal ore host stratum is the Boone
Formation, composed of fossiliferous dolomite, limestone and nodular chert.
Principal ore minerals are sphalerite and galena, with secondary concentrations
of chalcopyrite, enargite, luzonite, marcasite, pyrite, and barite. Significant
quantities of Pb and Zn were produced from the Tri-State District from the
1890s through the 1960s. By the late 1950s, depressed global markets resulted
in the suspension of most mining operations. By the early 1970s when mining
ceased, almost 2 million tons of Pb and 9 million tons of Zn had been produced.
The Tar Creek site was proposed for the Comprehensive Environmental Response,
Compensation, and Liability Act (Superfund) National Priorities List (NPL)
in 1981 and received final listing in 1983. Nearby are the Cherokee County
Superfund Site (Kansas) and the Oronogo-Duenweg Mining Belt and Newton County
Mines Superfund Sites (Missouri). The following information contains text
taken directly from Nairn et al. (2009).
In the Oklahoma portion of the district, approximately 1,000 hectares (ha) are underlain by underground mines in all or part of 47 sections. During mining, large-capacity dewatering operations pumped approximately 50,000 m3 of water per day from the mines. Upon decline and cessation of mining, groundwater began to accumulate in the mine voids. Approximately 94 million m3 of contaminated water exist in underground voids. By late 1979, metal-rich waters began to discharge into Tar Creek and its tributaries. The first documented discharge of mine drainage was at a location near southeast Commerce, Oklahoma, denoted by the Oklahoma Water Resources Board as Site 14.
Figure 1-1. Commerce/Mayer Ranch, Commerce, Ottawa County, Oklahoma.
Map created with ESRI ArcView software using Microsoft Bing maps.
2. Remedial Action and Technologies
Through a competitive bidding process, a design/build engineering contract
was awarded to CH2M-Hill using funds provided by the U.S. Environmental
Protection Agency and U.S. Geological Survey. The intent of this project
was to develop engineering plans and specifications for the design and
construction of the passive treatment system, build the system, and provide
as-built construction documents. Engineering design, based on the conceptual
designs and taking into account on-site conditions, was undertaken as an
iterative process between the design firm, the University of Oklahoma,
and EPA. To accommodate site constraints, multiple adjustments were made
to the system layout. Most notable of these included the configuration
of the system as two parallel flow paths to allow estimation of variance
in performance and to perform maintenance, consolidation of the layout
into a more compact “footprint” area to comply with construction requirements
adjacent to an existing utility corridor, and minimize impacts to adjacent
landowners, thereby creating a flatter hydraulic profile. Rotosonic overdrilling
of both mine drainage seeps was completed 18 months prior to passive treatment
system construction, thus providing hydraulic control and allowing additional
investigations to further quantify flow rates and variability.
Design and construction tasks included capture and control of the two known artesian mine drainage discharges, diversion of storm-water flows from a 470-ha upgradient watershed, implementation of all passive treatment process units including water conveyance structures, and provision of as-built documents. Design performance was estimated using inflow concentrations of 192 mg/L (Iron) Fe, 11 mg/L Zn, 17 µg/L (Cadmium) Cd and 60 µ/L Pb, and Fe removal rate of 20 grams per square meter per day with target Fe effluent of 1 mg/L and assuming net alkaline conditions, a discharge rate of 1000 L/minute, available site area of approximately 3.6 ha, and treatment area of 2 ha.
Construction began in July 2008 and was completed in late November 2008. Issues requiring resolution during construction and startup included the incorporation of a third seep (Seep D) into the inflow oxidation pond, removal of debris and existing iron oxide muck, delays throughout the course of construction caused by a record rainfall during the summer and related site water management issues, and changes in organic substrate requirements. The third seep was isolated as a distinct inflow into the first process unit and did not result in inflow discharge rates or mass loadings substantially different from initial designs. Based on additional laboratory work, the vertical-flow bioreactors received a mixture of 45% spent mushroom compost, 45% hardwood chips, and 10% manufactured limestone sand in the organic substrate layer. The total cost of design and construction totaled $1,196,000.
The completed system (Figure 2-1) includes 10 distinct process units with a single initial oxidation pond (cell 1) followed by parallel surface-flow aerobic wetlands/ponds (cells 2N and 2S), vertical-flow bioreactors (cells 3N and 3S), reaeration ponds (Cells 4N and 4S) and horizontal flow limestone beds (Cells 5N and 5S), and a single polishing pond/wetland (Cell 6). Mine water was diverted into the passive treatment system for the first time on December 2, 2008.
Figure 2-1. Completed remedial system.
3. Performance
Based on an extensive field data collection effort, laboratory and field
experiments, and a cooperative effort between academia, the private sector,
and government, the first full-scale passive treatment system in the Tri-State
Mining District was designed and constructed. This system represents a
start-of-the-art ecological engineering field research site. Although only
recently placed into operation, it is anticipated that this site will provide
data contributing to the enhancement of future passive treatment system
designs.
4. Costs
The cost of design and construction totaled $1,196,000.
5. Regulatory Challenges
The Tar Creek site was proposed for the Comprehensive Environmental Response,
Compensation and Liability Act (Superfund) NPL in 1981 and received final
listing in 1983. Nearby are the Cherokee County Superfund Site (Kansas),
and the Oronogo-Duenweg Mining Belt, and Newton County Mines Superfund
Sites in Missouri.
6. Stakeholder Challenges
There were no significant public or stakeholder issues associated with the
project.
7. Other Challenges and Lessons
Learned
No information was included with the case study.
8. References
Nairn, R. W., T. Beisel, R. C. Thomas, J. A. LaBar, K. A. Strevett, D. Fuller,
W. Strosnider, W. J. Andrews, J. Bays, and R. C. Knox. 2009. “Challenges
in Design and Construction of a Large Multi-Cell Passive Treatment System
for Ferruginous Lead-Zinc Mine Waters,” pp. 871–92 in Proceedings,
Joint Conference of American Society of Mining and Reclamation 26th Annual
Conference and 11th Billings Land Reclamation Symposium, Billings, Mont.