5. Construction

BCR performance depends on the care exercised during construction. Much of the construction is accomplished using heavy equipment, often in areas with poor or limited access, and by workers who may be more accustomed to less stringent design parameters. This chapter discusses the construction quality assurance (CQA) necessary during BCR system construction. Construction specifications, developed during the design phase of the project (Section 4.6) describe acceptable products and material specifications, alternatives, performance criteria and schedules to be followed by the construction contractors and confirmed by the site construction engineer.

Following the discussion of CQA are description of the construction features at a site using a BCR to treat MIW. These features include the following:

As a reminder, health and safety requirements during construction, operation and maintenance of BCR systems include those typical of remote construction projects that are also regulated by Occupational Safety and Health Administration (OSHA) and the Federal Mine Safety and Health Act, administered by the Mine Safety and Health Administration (MSHA), as applicable. In many instances training on excavation activities, confined space entry procedures, work with heavy machinery, power tools, uneven terrain, power tools, and work at and near contaminated sites can require 40-Hour Hazardous Waste Operations (OSHAOccupational Safety and Health Administration HAZWOPER) training for those workers that perform activities that expose or potentially expose them to hazardous substances during construction as well as during the treatment of hazardous substances.

Other regulations may apply to the siting of BCRs, including the Endangered Species Act of 1973 which protects the habitats of endangered species. On other sites artifacts or structures with cultural or historic value may be protected by The National Historic Preservation Act of 1966. In addition construction permits may be required from tribal, state, or local authorities. Please consult federal, tribal, state, and local requirements prior to construction.

5.1 Construction Quality Assurance (CQA) Plan

A Construction Quality Assurance Plan (CQA Plan) describes the construction quality assurance procedures in use during the BCR system construction activities. This plan is a recommended project submittal for the BCR based on the design requirements.

The CQA Plan addresses construction quality assurance procedures that are to be used to independently test and verify that the construction activities meet the intent of the design and conform to the construction specifications and drawings. The CQA Plan may be created by the Engineer as part of the design or by the Constructor as defined by the construction specifications. Example components of a CQA Plan are presented below, along with descriptions of key elements of a CQA Plan including definitions, construction quality control (QC) protocols, design modifications, clarifications, and changes, certification reports, and surveying.

5.1.1 Example Table of Contents for a CQA Plan

Table 5-1 presents an example table of contents for a CQA Plan applicable to construction of a BCR system. This example is not intended to be a definitive list of components of a CQA Plan as site-specific design may require different or alternative components.

5.1.2 Key features of the CQA Plan

5.1.2.1 Definitions

The following sections include example definitions for terms used in a CQA Plan. These definitions might be customized for different projects.

5.1.2.2 Construction Quality Control

Construction quality control functions are performed by the QC Monitor(s) during construction. The role of the QC Monitor, who is a representative of the Construction Contractors, is to report to the Construction Contractors and to provide construction support and controls so that the design specifications are achieved. The QC Monitor also must coordinate with the CQA Monitor and Engineer.

5.1.2.3 Design Modifications, Clarifications, and Changes

During construction, the need to document design and/or specification clarifications, modifications, and/or changes may arise. In such cases, the CQA Monitor should notify the Construction Manager and the Engineer of the need for any clarifications, modifications, or changes. This notification usually takes the form of a written agreement with documentation by the Engineer and acknowledgment by the Construction Manager. All design deficiencies and construction problems should be documented as well as any design modifications that resolve the issue. Documentation should generally include but not be limited to:

5.1.2.4 Certification Report

At the completion of the project, the Engineer should submit a Certification Report to the Project Manager and the Owner. This report certifies that the construction work was completed in compliance with the construction and shop drawings, project specifications, and related documents and be stamped by a registered (state) Professional Engineer. The report should include but not be limited to:

5.1.2.5 Surveying

Record survey documentation should be conducted as part of the Construction Contractor’s QC, with the CQA Monitor conducting periodic spot reviews and checks. The use of a Global Positioning System (GPS) receiver calibrated to the local site GPS network using site coordinates can assist in this documentation.

5.2 BCR Construction

5.2.1 Physical Settings

5.2.1.1 Siting the BCR System

Most passive treatment systems are located in remote, hard to access areas close to the source of MIW to treat. In some instances the mining-influenced water is captured and conveyed, piped, or pumped to the BCR system, which may be some distance from the MIW source.

Although the design of the BCR already considers numerous site-specific construction factors, finalizing the protocols, timing and procedures to bring construction equipment, materials and personnel to the BCR construction site is recommended. Constructing the BCR system during the early spring sometimes is recommended to avoid unnecessary vegetation clearing and avoid construction during rainy and winter seasons. Commissioning of BCR systems during the summer and fall are recommended. The local vegetation of the area takes a significant role where the influent water is routed to a convergence point because the plants can increase the dissolved oxygen (DO) of the MIW and may cause some metals to precipitate.

5.2.1.2 Water Influent Control System Installation

The simplest BCR water influent conveyance is the one that occurs naturally as a single stream that connects the MIW to the BCR system. The construction phase may call for increasing the stream side banks to match a specific maximum design flow that the BCR can support and channeling the water flow to the BCR influent structure. During intense precipitation events the maximum design flow may be surpassed and by-pass or diversion channels need to be constructed to relieve the excess flow to the BCR system. It is common to construct an influent bypass during construction and/or in high flow conditions. A by-pass box can be designed such that the excess overflow is diverted hydraulically using an overflow weir to the by-pass system.

5.2.2 BCR Typical Construction

This section presents guidance on typical construction aspects of a BCR unit, including site preparation, liner installation, process piping installation, substrate installation, and cover installation. Although the overall treatment system may consist of the BCR unit, influent and effluent components, and pre- and post- treatment components, this section focuses on construction of the BCR unit component, and also presents general discussion of the relation of the BCR unit construction to other components of the overall treatment system.

5.2.2.1 BCR Site Preparation

Construction of a BCR system begins with preparing the site area. The site preparation task for the BCR unit includes, but is not limited to:

5.2.2.2 Liner Installation

The base or floor of the BCR unit may be constructed in a number of different ways depending on site conditions. In the majority of cases, a liner is specified to prevent seepage of surrounding groundwater into the BCR unit or leakage of MIW from the BCR unit. In the case that the BCR unit is constructed within native clay or similar low-permeability soil, a liner may not be required. However, adequate testing of the soil conditions should be conducted to ensure that the BCR unit holds water.

5.2.2.3 Process Piping Installation

Process piping for BCR systems includes influent and effluent piping outside of the BCR unit, and piping within the BCR unit. As for site preparation tasks, it is critical to install process piping to meet the grading, pipe material type, and pipe connection requirements prescribed by the design. These elements are critical to success of a long-term functioning system. Typical process piping material for BCR systems are PVC, smooth-walled HDPEhigh density polyethylene and corrugated HDPE. Within the BCR unit, PVC or corrugated HDPEhigh density polyethylene piping is most common because of lower price and ease of installation. Effluent collection piping for a downflow BCR unit is also typically perforated. Effluent for an upflow BCR unit may not require effluent piping, rather the system is graded to drain by overflow at the top of the unit although during high flow conditions the potential for short-circuiting at the BCR may be observed if not designed properly.

5.2.2.4 Substrate Installation

As discussed in detail in Section 3.1, the substrate for a BCR can include a number of different materials. The substrate in a BCR is the main component by which the MIW is treated. Typical BCRs include solid substrate materials placed in the unit. In some cases, liquid substrates may be added to the influent stream. The types and proportions of materials are developed in the design based on results of the bench and pilot testing that indicate the best treatment approach for the site MIW. As such, the proper proportioning of substrate materials for the full-scale system is vital to the success of the reactor to adequately treat the MIW. If not done during the testing phase, the substrate materials should undergo comprehensive testing for incidental contaminants that could be introduced into the system.

5.2.2.5 Cover Installation

As determined by the design, a cover over the substrate layer may be beneficial. This determination is mostly based on climate (Section 2.6). Cold winter climates can have adverse effects to the BCR unit sulfate reductionThe stripping of oxygen atoms from sulfate (SO₄²⁻), most often yielding sulfide (S²⁻) as an ultimate product. rate due to the low temperature. Also, a cover may be desired based on the designers’ preference and experience. Covers can also help with reduction in odor issues caused by hydrogen sulfide gas production from the sulfate reduction reaction.

5.2.2.6 BCR Systems Effluent Control Installation

Treated effluent from a BCR can leave from a constant elevation overflow pipe via an open or valved piping system, or as an overflow pipe or overflow spillway from the BCR. There are also adjustable water head control valve boxes that allows a predetermined water head in the BCR unit to be maintained. Figures 5-5 and 5-6 present a constant head overflow discharge pipe and an adjustable head overflow device, respectively.

Figure 5-5. Example constant elevation BCR overflow discharge.

Figure 5-6. Adjustable elevation head weir for BCR effluent.

Mechanical failures from the effluent system include the freezing of the effluent control valve that controls the effluent for the BCR, if present. Although a good valve exercise program minimizes the potential for the valves to become stuck, the presence of solid mineral deposits including iron and other metal hydroxides or sulfides make the BCR effluent valves susceptible to failure. Also, the adjustable weir boxes used in BCR effluent systems are also prone to become stuck due to the presence of mineral build up.

5.2.3 BCR Systems Performance and Monitoring Equipment Installation

The BCR units are constructed with some monitoring wells and piezometers that allow for monitoring the performance of the BCRs as well as the performance of the BCR liner. Figure 5-7 presents a BCR with monitoring wells and piezometers. In addition, there may be monitoring ports within the BCR itself (see Section 4.3.4). These are normally used to ensure that the hydraulics of the BCR are acceptable and that there is no apparent short circuiting of flow as well as providing a location where water samples can be collected within the BCR unit. These monitoring wells can provide information on the performance of the BCR, the location of the anoxic zone, and location where substrate may be compromised.

Figure 5-7. BCR monitoring wells and appurtenances.

5.2.4 BCR Systems Site Construction Restoration

The BCR system design drawings and specifications normally include a section on the site construction restoration that includes the minimum restoration design criteria after the BCR system is built. Site restoration can call for re-establishing the site not occupied by the BCR system to its original state, matching existing conditions to the area surrounding the work site or partially restoring areas, allowing access roads, building, and specific features to remain.

As the site restoration takes place, field QC of restoration activities may require approval by stakeholders, such as the appropriate grass seeding mix needed as well as documentation of restoration activities and meeting site restoration conditions. After topsoil placement and grading is complete, the surface is normally roughened (raked) prior to applying fertilizer and grass seed. The topsoil is loosely compacted to promote growth.

Following placement of the impermeable geo-membrane over the bioreactor, general backfill and topsoil are often placed and loosely compacted with a final grade normally 1-foot above the surrounding grade to allow for surface runoff. Final grade along the perimeter of the BCR Unit can gradually blend into the surrounding surface grade.

All remaining disturbed areas (such as backfilled trenches, monitoring well completions, stockpile areas, haul routes, and support construction areas) may need to be restored to conditions similar to or better than pre-construction conditions. This restoration may include the addition of topsoil, fertilizer, and seeding as required.

Restored areas are normally maintained, protected, and sometimes fenced to limit access to the BCR system site. All restoration activities are normally coordinated with the owner or owner’s representatives to ensure that restored areas are completed to their satisfaction.

5.2.5 Site Security

During BCR system construction, all visitors to the work site are normally required to report to the site construction manager as soon as they arrive on site. The area immediately surrounding the BCR system construction work area is normally marked through the use of signs, barrier rope or tape, or fencing. BCR system security is designed to prevent exposure of unauthorized, unprotected individuals to the work areas.

Due to their generally remote locations, BCR system construction site security can range from nonexistent to chained-linked wire fence, depending on the location of the BCR system and its proximity to urban areas. More sophisticated security systems such as camera and motion detector-based surveillance systems are normally not necessary as part of the BCR system construction, but may be necessary if the BCR system is adjacent to a site that requires surveillance.

 

 

Publication Date: November 2013

Permission is granted to refer to or quote from this publication with the customary acknowledgment of the source (see suggested citation and disclaimer).

 

This web site is owned by ITRC.

1250 H Street, NW • Suite 850 • Washington, DC 20005

(202) 266-4933 • Email: [email protected]

Terms of Service, Privacy Policy, and Usage Policy

 

ITRC is sponsored by the Environmental Council of the States.